Projects
Childers Cove Road (Rural Road) – Between chainage 6.800 kilometres and 8.260 kilometres measured from start. The road pavement and surface has significantly deteriorated.
Aire Street, Kirkstall – Between chainage 0.125 kilometres and 0.445 kilometres measured from start. Gravel road wearing due to increase of traffic and heavy
Boundary Road (Rural road) – Between 5.10km and 8.28km measured from Timboon Curdievale Road Project completed: 1 March 2026 Funding Source | Australian Government:
Pontings Road, Terang – Between 2.10 km and 5.54 km measured from Princes Highway. (Resealing) Project completed: 31 March 2026 Funding Source | Australian
Timboon Curdievale Road, Timboon – Between 0.22km and 1.02km measured from Timboon Nullawarre Road. Project completed: 1 April 2026 Funding Source | Australian Government:
Leahys Lane, Timboon – Between 0.51km and 0.63km measured from Timboon Curdievale Road. Project completed: 1 April 2026 Funding Source | Australian Government: $173,352.00
Burkes Road, Terang – Between 0km and 0.18km measured from Thomson Street. Project completed: 1 April 2026 Funding Source | Australian Government: $228,995.00
Nareen Road (Rural road) – Measured from start point 3.29km – Boorook Road. (Bridges & Culverts). Project completed: 1 March 2026 Funding Source |
Koallah Road (Rural road) – Between 1.5km and 2.27km measured from Princes Highway. Project completed: 1 April 2026 Funding Source | Australian Government: $359,372.00
Gnarpurt Road (Rural Road) – Between 10.91km and 11.53km measured from Foxhow Road. Project completed: 1 December 2025 Funding Source | Australian Government: $311,862.00
Noogee Road (Rural Road) – Between 0km and 2.05km measured from Princes Highway. Project completed: 1 April 2026 Funding Source | Australian Government: $824,872.00
Sisters-Noorat Road (Rural Road) Project completed: 1 January 2026 Funding Source | Australian Government: $480,775.00
Linton Road (Rural Road) – Between 14.59km and 15.48km measured from Hamilton Highway. Project completed: 1 March 2026 Funding Source | Australian Government: $350,587.00
Batemans Road (Rural Road) – Between 3.35 km and 4.01 km measured from Princes Highway. Project completed: 1 April 2025 Funding Source | Australian
Danedite Road (Rural Road) – Between 2.41 km and 3.49 km measured from Princes Highway. Project completed: 1 April 2025 Funding Source | Australian